Challenging scaffolding project

Norisol A/S

Approximately DKK 700,000

NNE / Novo Nordisk

2022

A challenging scaffolding project

A new pipe bridge has been built over a railroad in Kalundborg between new and old factories at Novo Nordisk. The pipe bridge will carry supply pipes between the factory buildings.

To allow for maintenance and repair of the pipe bridge, we built a scaffold on the ground in 3 sections and then lifted it onto the pipe bridge by crane and assembled it on the bridge. The suspension itself took 4 hours from 21:30 - 01:30 and the train traffic was stopped during the period.

The complexity of this special project was the many calculations and extensive planning. Many external parties were involved, which also contributed to the time required.

However, everything went as planned. Our well-trained, experienced employees put in a great effort and the scaffolding was ready and functional by the deadline.