Project Description

DESCRIPTION

Insulation and cladding of drying chamber with adjoining ducts and pipes at biorefinery.

The drying chamber are in three sections with a total height of 30 metres and a diameter of 11 metres. The insulation material is mineral wool and cladding is trapezoidal profiled sheet metal.

Part of the cladding for the ducts were pre produced at Norisol’s workshop in Fredericia, Denmark. The ducts have a diameter of 1800 mm.

Fitters from Norisol, Denmark carried out the installation work in Norway.

PROJECT DATA

Time of Execution
2018